To fully restore the Keele main substation now that Toronto Hydro has completed its improvements to the Keele Street sources, the following buildings will experience a 15-minute power interruption (except as noted) on Friday, March 27, between 6:30 and 7am:
- Chemistry Building (momentary outage)
- Life Sciences Building (momentary outage)
- Lassonde Building (momentary outage)
- Steacie Science & Engineering Library (momentary outage)
- Vanier College
- Vanier Residence
- Founders College
- Founders Residence
- Ross Building
- Central Square
- Curtis Lecture Halls
- Student Centre
- William Small Centre
- Arboretum Lane Parking Garage
- new engineering building construction trailers
- Harry Crowe Apartments
- Ignat Kaneff Building, Osgoode Hall Law School
- Hart House
- Hoover Houses
- #380 Assiniboine Road
- #320 Assiniboine Road
- Atkinson Residences
- Vari Hall
- Physical Resources Building
- 190 Albany Road
During this interruption, campus steam will be delivered at a reduced capacity.
Questions and concerns about this outage can be directed to Shawn Payne, assistant chief engineer, at ext. 55623, or Gary Gazo, medium voltage distribution engineer, at ext. 20949. For any concerns during the interruption, contact Security at ext. 33333.